Growth & Development, Tracked
Who decides how Bedford County grows — and what they're deciding now
Growth decisions here are split between governments: the county Planning Commission and Board of Commissioners govern unincorporated land, and each city council — Shelbyville above all — governs its own limits. This page tracks both, item by item, with the official document or recording beside every claim. Open Bedford takes no position on growth.
Statements made in meetings are attributed to the record — official minutes where they exist, or the county's own meeting video at a linked timestamp where they don't. The county publishes no minutes for its Planning Commission, so for that body the video is the record. Transcript links below are unofficial machine-generated mirrors of YouTube's captions; every line links back to the recording.
Being Decided Right Now — County
Minimum road width for major subdivisions
Pending — resolution due back to the Planning CommissionHow wide must an existing county road be before a major subdivision can be approved on it? The draft rule presented to the county Planning Commission on July 28, 2026 set the minimum at 18 feet — a figure the planning director told the commission he and Road Superintendent Mark Clanton had landed on (video, 1:19:50), adding that if the body wanted 20 feet he was fine with that (1:20:06). In the discussion that followed, members and the superintendent spoke in favor of 20 feet, and the chair asked for a show of hands on 20 feet while stating it was not a vote (1:46:37). The planning director said he would bring a formal resolution back the next month with whatever figure the commission directed (1:36:20). No vote has been taken; nothing is adopted until the commission adopts it.
How many lots can be split off without full review
Pending — part of the subdivision-regulation rewriteA "simple" subdivision can be approved administratively, without coming before the Planning Commission. The planning director's proposal, described at the July 28 meeting, would cut the simple-subdivision limit from five lots to three lots (video, 1:54:03), with a waiting period before the same parent tract can be split again. The proposal as described used a 12-month period; a member asked for 24 months (1:49:14), and the closing discussion ran in that direction — three lots, then major-subdivision review, with a 24-month period (1:57:08, 1:59:00). The idea of tightening the limit was first raised at the June 23 meeting (video, 37:28). Subdivision-regulation changes require a public hearing before adoption — see the Planning Commission tracker. No vote has been taken.
The comprehensive growth plan — first draft under review
Draft review in progress — public engagement to followThe county Planning Commission is reading a draft Comprehensive Plan section by section: members were assigned pages 1–32 after the June 23 meeting (video, 58:04), reviewed pages 34–62 on July 28 (video, 22:07), and were assigned pages 65–95 for the next meeting (1:15:14). The planning director told the commission he wants "a robust public engagement process" on the plan before adoption, giving the public the same chance to dig into the draft that commissioners have (24:51). When that engagement phase is announced, it will appear in Open Bedford's meeting coverage.
Also in motion: a proposed one-year moratorium on large-scale data centers — covered in full in the data centers explainer. The complete item-by-item docket lives on the Planning page.
Recent Decisions, With the Votes
Remington Farms PUD — approved by the Shelbyville City Council, 4–2
Decided May 14, 2026On second and final reading, the Shelbyville City Council approved the ordinance adopting the Remington Farms Planned Unit Development pattern book and rezoning approximately 158 acres on Union Street (Tax Map 079, Parcels 047.00, 047.02, 047.03) to Planned Unit Development. The ordinance caption itself records that the Shelbyville Municipal Planning Commission had recommended it unfavorably. The minutes record the final unit number as 480, with 345 being single-family residences.
The roll-call vote, as the official minutes record it: Noel — Yes, Christie — No, Blevins — No, Turnbow — Yes, Feldhaus — Yes, Ewing — Yes.
Five residents addressed the item, per the minutes: Terry Breit spoke against, stating the Council should not ignore the Planning Commission recommendation and that Highway 41A needs upgrading first; Jeff Clark and David Molder spoke in favor; Randolph Kelly asked the Council to listen to the Planning Commission —
"They are not saying no to the development, they are saying the infrastructure is not there." — Randolph Kelly, as recorded in the official minutes, May 14, 2026
— and Samantha Guthrie spoke against the rezoning during the public hearing. Councilmember Blevins, voting no, is recorded stating the vote was "not on a developer but on a development" and that "the product on paper does not meet the standards of infrastructure going forward"; Councilmember Ewing, voting yes, is recorded stating the developer has made a lot of changes and the development will happen in phases. Dan Bobo, on behalf of the developer, is recorded describing improvements including sewer fees paid, a donated future school site, and an agreed Highway 41A improvement.
933 West Jackson Street rezoning — sent back to the planning commission, 3–2
Returned April 9, 2026 — still pendingA first-reading ordinance would rezone approximately 14 acres known as the Patterson Addition, at 933 West Jackson Street (Tax Map 088, Parcel 062.00), from I-1 Light Industrial to R-3 Medium Density Residential. Instead of voting on the ordinance, the Council voted on Councilmember Turnbow's motion to return the item to the planning commission "and not bring back until something that works is worked out." The roll-call vote, as the minutes record it: Blevins — No, Turnbow — Yes, Feldhaus — Yes, Ewing — Yes, Christie — No. The City Attorney advised that because the vote was on the motion to defer, not the ordinance itself, a quorum vote was not required — so the motion carried 3–2 and the item went back to the planning commission. In public comment, resident Chuck Glover is recorded stating he has lived in front of the site for over 35 years and has seen the area flood; the property owner, Courtney Clardy, is recorded stating the land is not unusable and that nothing can be done until FEMA approval.
Driveway permits on county roads — adopted by the County Commission
Decided May 12, 2026The Bedford County Board of Commissioners approved the Highway Department's permit guidelines: motion by Smith, seconded by Davis, passed unanimously by voice vote. The guidelines attached to the minutes — issued under Road Superintendent Mark Clanton — require a driveway permit before constructing a driveway that connects to a county road, set the permit fee at $50.00, require drain tile of at least 12 inches, and provide that code inspectors will not issue a certificate of occupancy without a signed driveway permit. The superintendent had described the plan to the Planning Commission on April 28: the $50 fee pays for field inspections, and the concern he cited was new construction — subdivisions where some driveways get culverts and some don't (video, 21:58, 20:49). On July 28 he told the Planning Commission the permit is now in use on developments (video, 1:33:31).
2640 Highway 41-A North rezoned A-1 to C-1
Decided May 12, 2026The County Commission rezoned the property at 2640 Highway 41-A North (Tax Map 048, Parcel 033.01) from A-1 Agriculture-Forestry to C-1 Rural Center District, to allow a grading and excavation business office and parking/storage of construction equipment. The county Planning Commission had recommended the rezoning unanimously on February 24; no one spoke at the public hearing; the Commission passed it unanimously by voice vote.
The Numbers Officials Cite
These figures come from statements made on the record in county Planning Commission meetings. They are reported here as stated, by whom, and where — Open Bedford has not independently verified them, and the documents that would verify them appear in the "not yet documented" table below.
- Five platted subdivisions, 187 lots, in the unincorporated county over five years. The planning director told the June 23 meeting that from 2021 to 2026 the county approved five platted subdivisions — of 22, 40, 75, 38, and 12 lots — totaling 187 lots (video, 39:03).
- "More than 2,300 lots" approved by the City of Shelbyville over the same period — the comparison the planning director drew in the same statement, adding, in the words of the recording, "the growth problem is not in the rural area" (video, 39:28).
- About 4.18% five-year growth in the unincorporated county. At the February 24 meeting the planning director said he "did the numbers" for the unincorporated areas over the last five years and put growth at about 4.18%, which he described as below normal, while noting the city's five-year picture is different (video, 40:37).
Attribution note: the county's meeting videos carry no speaker labels; these attributions follow the meeting context, in which the speaker conducts the planning department's business and refers to himself as the planning director (e.g., July 28, 1:39:02). Every timestamp lets you check the statement against the recording yourself.
Follow It Yourself
The four county Planning Commission meetings covered on this page are readable end-to-end as unofficial transcript mirrors — every line links to its moment in the county's own video:
- Planning Commission, February 24, 2026 — comprehensive plan; growth figures.
- Planning Commission, April 28, 2026 — driveway permit proposal; quarry discussion.
- Planning Commission, June 23, 2026 — subdivision counts; data-center moratorium request; plan review.
- Planning Commission, July 28, 2026 — road width; lot limits; plan pages 34–62.
The live docket is on the Planning page; schedules, agendas, and how to attend are on the Meetings page; the data-center moratorium has its own explainer, as does quarrying near Wartrace.
What Isn't Publicly Documented Yet
Each open question below is answerable by a specific public document. As those documents are obtained, this page fills in.
| Open question | The document that would answer it |
|---|---|
| What exact road-width, lot-limit, and driveway text will the Planning Commission adopt? | The subdivision-regulation resolution when it appears on a Planning Commission agenda, and the adopted regulation text |
| What does the draft Comprehensive Plan actually say? | The draft document the commission is reviewing — obtainable from the county planning office; this page will link it when the county publishes it |
| Do the cited growth figures — 187 county lots, 2,300 city lots, 4.18% — match the plats and permits? | Recorded plats (Register of Deeds), City of Shelbyville planning commission records, and the data source behind the growth percentage |
| What does the Remington Farms traffic study show, and what did the pattern book promise? | City of Shelbyville planning file for the Remington Farms PUD (traffic study, pattern book, development agreement) |
| What happens next at 933 West Jackson Street? | Shelbyville Municipal Planning Commission agendas and minutes after April 9, 2026 |
| What did the county Planning Commission formally decide at each meeting? | The county publishes no Planning Commission minutes online — the agenda and video are the record; a records request could obtain any written record kept |
Look It Up Yourself
Every source this page uses is public:
- Bedford County Zoning Resolution (PDF) — what each district allows, countywide.
- County Commission minutes, May 12, 2026 (PDF) — roll call, votes, and the driveway-permit guidelines as adopted.
- Shelbyville City Council minutes, May 14, 2026 (PDF) and April 9, 2026 (PDF) — the city votes reported above, verbatim.
- Shelbyville Gov TV on YouTube — city meeting video, including the May 2026 regular session.
- Tennessee Property Assessment Data — ownership, acreage, and classification for any parcel named above (pick Bedford County).
Have a document?
Open Bedford works from documents, not tips. If you hold a record that answers one of the open questions above — a plat, a study, a staff report, a letter — send it to josh@openbedford.org or use the "Uncover Something" box on the homepage. Documents are archived with provenance before anything is published from them.